Instructions

68RFE 2C Install Instructions

The 2C stack up we designed is engineered to never allow the friction to fall below the 2C reaction planet. We do this with a custom thickness 2C billet piston and thin steel added into the stack up.
68RFE 2C Install Instructions

Thank you for your purchase with WP Developments! The 2C stack up we designed is engineered to never allow the friction to fall below the 2C reaction planet. We do this with a custom thickness 2C billet piston and thin steel added into the stack up.

Stack Order

  1. Thick factory reaction plate in the case as normal.
  2. .062 (sometimes this can be a.068 but the piston will be machined to match the thickness) steel
  3. Friction
  4. Steel 
  5. Friction
  6. Steel
  7. Friction
  8. Ending on a steel 

Phone: (765) 586-0871

Email: sales@wp-developments.com

We want to see your builds! Snag a few pictures of our products installed on your project, post them and tag our social media linked below or feel free to send them to us via text or email!

Full Article

Interested in our 68RFE Converters?

Please fill out our form below to let us know if you are interested.
Thank you for submitting your contact information! We appreciate your interest and look forward to connecting with you.
Oops! Something went wrong while submitting the form.

Transmission Tech Videos

Related Transmission Parts

Latest Tech Tips

Learn from our latest tech tips, videos, articles, and podcast appearances.

Article

WP Built 68RFE Torque Converters Coming Soon

WP Development's announces their own line of high performance 68RFE torque converters.

Learn More

Job Posting

Now Hiring: Sales and Marketing Manager

WP Developments is looking to hire a Sales and Marketing Manager on-site.

Learn More

Article

10L1000 Transmission Clutch Clearance and Torque Specifications

Find clutch clearance and torque spec information for your next 10L1000 transmission rebuild.

Learn More